Task Report: Requirements & Modeling FYP Plan

Task Start End Duration Completed Dependencies Constraint Start
0)Modeling Requirements of Catering Experience at Cardiff University 11/10/2012 08:00 03/05/2013 08:00 29w 1d 1%
1) Project Plan 11/10/2012 08:00 17/10/2012 17:00 1w 80%
2) Identify Requirements Methodologies 12/10/2012 16:30 16/11/2012 16:30 5w 4% 12/10/2012 16:30
3) Identify and Investigate Requirements Elicitation Techniques 22/10/2012 08:30 05/11/2012 08:30 2w 0% 22/10/2012 08:30
4) Submission of Project Plan 19/10/2012 09:00 19/10/2012 09:00 0% 1 19/10/2012 09:00
5) Investigate Key Stake holders 22/10/2012 08:00 26/10/2012 17:00 1w 0% 22/10/2012 08:00
6) Define Suitable Elicitation Techniques for the Specific Stakeholders - Groups 29/10/2012 08:00 02/11/2012 17:00 1w 0% 5 29/10/2012 08:00
7) Assess The Business Requirements of the Universities Catering Team 22/10/2012 08:30 05/11/2012 08:30 2w 0% 22/10/2012 08:30
8) Collect Documentation 29/10/2012 08:00 09/11/2012 17:00 2w 0% 29/10/2012 08:00
9) Initiate Implementation of Elicitation Techniques 05/11/2012 08:00 16/11/2012 16:30 < 1w 5d 0% 6 05/11/2012 08:00
10) Continued Implementation of Elicitation Techniques 19/11/2012 08:00 22/03/2013 16:30 < 17w 5d 0% 19/11/2012 08:00
11) Assessed Their Effectiveness 07/11/2012 16:00 19/11/2012 10:30 < 1w 2.5d 0% 9FF 07/11/2012 16:00
12) Produced Interim Report 19/11/2012 08:30 13/12/2012 08:30 3w 3d 0% 19/11/2012 08:30
13) Formulate Questionnaire Questions 09/11/2012 16:30 16/11/2012 16:00 < 5d 0% 09/11/2012 16:30
14) Produce a Questionnaire 16/11/2012 16:30 23/11/2012 16:30 1w 0% 13 16/11/2012 16:30
15) Formulate Interviewee Questions 23/11/2012 16:00 30/11/2012 16:00 1w 0% 2 23/11/2012 16:00
16) Test Interview Questions on a Course Mate 30/11/2012 16:30 04/12/2012 08:30 > 1d 0% 15 30/11/2012 16:30
17) Evaluate Interview Questions 04/12/2012 08:30 05/12/2012 08:30 1d 0% 16 04/12/2012 08:30
18) Interview Followup 21/01/2013 08:00 25/01/2013 17:00 1w 0% 21/01/2013 08:00
19) Formulate Interviewee Questions 01/02/2013 16:00 08/02/2013 16:00 1w 0% 2 01/02/2013 16:00
20) Test Interview Questions on a Course Mate 08/02/2013 16:30 12/02/2013 08:30 > 1d 0% 19 08/02/2013 16:30
21) Evaluate Interview Questions 12/02/2013 08:30 13/02/2013 08:30 1d 0% 20 12/02/2013 08:30
22) Interview Follow-up 18/02/2013 08:00 22/02/2013 17:00 1w 0% 18/02/2013 08:00
23) Build Requirements Template 12/11/2012 08:00 16/11/2012 17:00 1w 0% 12/11/2012 08:00
24) Populate Requirements Documentation (ongoing) 19/11/2012 08:00 25/03/2013 08:30 > 18w 0% 19/11/2012 08:00
25) Submission of Interim Report 14/12/2012 08:30 14/12/2012 08:30 0% 12FF 14/12/2012 08:30
26) Market Competition 25/02/2013 08:30 01/03/2013 16:30 > 4.75d 0% 25/02/2013 08:30
27) Build Requirements Taxonomy 21/01/2013 08:00 15/02/2013 17:00 4w 0% 21/01/2013 08:00
28) Produce FInal Report 01/04/2013 08:00 26/04/2013 16:30 < 3w 5d 0% 01/04/2013 08:00
29) Submission of Final Report 03/05/2013 08:00 03/05/2013 08:00 0% 28FF 03/05/2013 08:00
30) Produce a Forum for Student Unstructured Feedback 21/01/2013 08:30 28/01/2013 09:00 > 1w 0% 21/01/2013 08:30
31) Produce Relevant Topics for the Forum, Polls etc. 28/01/2013 09:00 04/02/2013 08:30 < 5d 0% 30 28/01/2013 08:30
32) Produce a Poster for the Forum 07/02/2013 14:30 08/02/2013 14:30 1d 0% 30FF 07/02/2013 14:30
33) Investigate the Applicability of Unstructured Student Feedback 21/01/2013 08:30 08/02/2013 16:30 > 2w 4.75d 0% 32FF 21/01/2013 08:30
34) Develop Uses Cases 28/01/2013 08:00 18/02/2013 08:30 > 3w 0% 28/01/2013 08:00
35) Focus Groups 11/02/2013 08:00 15/02/2013 17:00 1w 0% 11/02/2013 08:00
36) Focus Group Follow-up 18/02/2013 08:00 20/02/2013 11:30 < 2.5d 0% 18/02/2013 08:00
37) Gap Analysis from Current Working Practices to Those Identified From the Requirements 04/03/2013 08:00 15/03/2013 16:00 > 1w 4.75d 0% 04/03/2013 08:00
38) Develop Business Plan to go Forward 18/03/2013 08:00 01/04/2013 08:30 > 2w 0% 18/03/2013 08:00